Water Supply & Fire Extinguisher Line

An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Case Study Nº

49

Customer

Cheddi Jagan International Airport
Guyana

|

2018

Working Conditions

Water: 6 bar | Hydrants: 12 bar Indoor | Sprinklers: 18 bar

Pexgol Pipes

Pexgol 110, 125, 160 & 225 mm 32 Class 19

Application

Water Supply & Fire Extinguisher Line

Lenght

Categories

The Challenge

Cheddi Jagan International Airport were going under renovations in order to expand their operations.
One of the main challenges for them was installing a fire extinguishing line all over the airport. The main concern for the engineering company (China Harbour) that was caring out the project was to find a suitable pipe line that required minimum maintenance, a material that can withstand hard installation conditions and minimum possible installation time, since this kind of lines usually requires a lot of work.

The other challenge was the installation of the water supply line. The conditions were also hard and they required a pipe in compliance with ASME standards.

Pexgol Solution

The Designer Engineer required China Harbour to install PE-x pipes for both lines.
Pexgol pipe systems was chosen due to its capabilities that allow the pipes to be drag on concrete, steel and all over the construction site making the installation efficient and fast. With other materials such as PE, tons of precautions to not damage should been necessary.
Pexgol pipes were also a great solution regarding possible water hammers caused by the hydrant trucks in case a fire develops, since the pipe can withstand them.

The pipes were connected with mechanical fittings, and they also didn’t required special treatment.
The installation with Pexgol pipes took x2.5 times less than any other material like PE. This pipes would have required special care to install the fittings, a much longer installation time and detailed supervision.
During the installation, local workers were trained on the field and complete the installation with great success.

Related Case Studies

Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Replacement of a HDPE Pipe for a Pexgol Pipe

Slurry Transportation

Sabinas Mine
Mexico

 | 

2017
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025