Water Supply & Fire Extinguisher Line

An Outdoor Hydrant and Indoor Sprinklers were installed at Guyana Airport

Estudo de Caso Nº

49

Cliente

Cheddi Jagan International Airport
Guyana

|

2018

Condições de Trabalho

Water: 6 bar | Hydrants: 12 bar Indoor | Sprinklers: 18 bar

Solução Pexgol

Pexgol 110, 125, 160 & 225 mm 32 Class 19

Aplicação

Water Supply & Fire Extinguisher Line

Comprimento

Categorias

The Challenge

Cheddi Jagan International Airport were going under renovations in order to expand their operations.
One of the main challenges for them was installing a fire extinguishing line all over the airport. The main concern for the engineering company (China Harbour) that was caring out the project was to find a suitable pipe line that required minimum maintenance, a material that can withstand hard installation conditions and minimum possible installation time, since this kind of lines usually requires a lot of work.

The other challenge was the installation of the water supply line. The conditions were also hard and they required a pipe in compliance with ASME standards.

Pexgol Solution

The Designer Engineer required China Harbour to install PE-x pipes for both lines.
Pexgol pipe systems was chosen due to its capabilities that allow the pipes to be drag on concrete, steel and all over the construction site making the installation efficient and fast. With other materials such as PE, tons of precautions to not damage should been necessary.
Pexgol pipes were also a great solution regarding possible water hammers caused by the hydrant trucks in case a fire develops, since the pipe can withstand them.

The pipes were connected with mechanical fittings, and they also didn’t required special treatment.
The installation with Pexgol pipes took x2.5 times less than any other material like PE. This pipes would have required special care to install the fittings, a much longer installation time and detailed supervision.
During the installation, local workers were trained on the field and complete the installation with great success.

Estudos de Caso Relacionados

Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020
Grey Water Transportation

Recovered Water Transportation

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

 | 

2017
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018