Skip to content

Cold Water Distribution for External Cooler System

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Case Study Nº

115

Customer

Chip Manufacturer
Israel

|

2022

Working Conditions

Pressure: 6 bars | Temperature: 8°C / 46°F

Pexgol Pipes

Pexgol 355 (14″), 400 (16″) & 630 (24″) mm, Class 15

Application

External Chiller System

Lenght

160 m / 525 ft

Categories

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to increase the capacity of energy in the factory by adding an external chiller system and they needed to finish the installation and implementation as soon as possible.

Pexgol Solution

Due to a successful experience in the past, the company decided to use Pexgol pipes due to the fast installation time, helping to maintain their operation schedule and reduce the total cost of the project.

Related Case Studies

Монтаж труб Pexgol для транспортировки горячей воды

Горячее водоснабжение

Hilton
Израиль

 | 

2020
Транспортировка воды более чем на 150 карьерных транспортных развязках

Транспортировка воды на транспортных развязках

Компания Doña Inés de Collahuasi SCM, шахта Collahuasi
Чили

 | 

2012
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Осушение шахты в условиях высокого давления

Осушение шахты — в условиях высокого давления

Antofagasta Minerals, шахта «Михилья»
Чили

 | 

2011
Вычерпываемый шлам с крупнозернистым NaCl (соль)

Шламовые линии. Абразивныйвыбранный грунт

Группа ICL, работы на Мертвом море
Израиль

 | 

1992
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023