Skip to content

2,900 Meters of Pexgol Installed and Pressure-Tested in Just 3 Days

Pexgol reduced the number of joints, accelerated installation, and improved network reliability.

Case Study Nº

195

Customer

Petróleos Sudamericanos
Argentina

|

2026

Working Conditions

Operating pressure: 6 kg/cm² / 85 psi | Temperature: 30°C / 86°F | Flow rate: 40,000 m³/day | Transported material: Treated methane gas, 100% dry

Pexgol Pipes

Pexgol 110 mm, Class 10

Application

Dry gas / treated methane transportation

Lenght

2,900 m / 9,514 ft

Categories

2,900 Meters of Pexgol Installed and Pressure-Tested in Just 3 Days

The Challenge

Petróleos Sudamericanos S.A., an energy company with more than 30 years of experience in oil and gas exploration and production, needed to replace an existing dry gas transportation pipeline in Catriel, Río Negro, Argentina.

The previous carbon steel pipeline had been in service for many years and was showing signs of corrosion and wear. To ensure operational continuity and improve system reliability, the client required an alternative capable of transporting treated methane gas, 100% dry, under operating conditions of 6 kg/cm² pressure, a temperature of 30°C / 86°F, and a flow rate of 40,000 m³/day.

In addition to material resistance, the project required an efficient installation process with fewer joints and shorter field execution times.

The Solution

For this project, 2,900 m / 9,514 ft of 110 mm, Class 10 Pexgol pipe were installed for dry gas transportation.

Thanks to its flexibility, low weight, and availability in long sections, Pexgol made it possible to complete the installation and pneumatic pressure test in just three days. Only six joints were required along the entire 2.9 km / 1.8 mi pipeline, significantly reducing critical points and improving network safety.

Pexgol’s corrosion resistance, ease of handling, and long service life made it an ideal solution for replacing the existing metallic pipeline.

This was the contractor’s second project using Pexgol. After gaining experience with the material during the first installation, the contractor selected Pexgol again due to its ease of installation and operational advantages over traditional piping solutions.

Related Case Studies

Линия питьевой воды высокого давления

Линия питьевой воды высокого давления

Компания Antofagasta Minerals, шахта Pelambres
Чили

 | 

2014
Монтаж труб Pexgol для транспортировки рыбы.

Линии разгрузки рыбы

TASA
Перу

 | 

2018
Работа с высоким давлением и предельными температурами окружающей среды

Транспортировка воды на медном руднике

Рудник Zaldivar SPA
Чили

 | 

2018
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Линии подачи пресс-фильтра LASTA2

Транспортировка концентрированной медной руды

Компания BHP Billiton, месторождение, Olympic Dam, Австралия
Австралия

 | 

2014