High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Case Study Nº

102

Customer

Lundin Mining
Chile

|

2021

Working Conditions

Flow: 720 m3/h

Pexgol Pipes

Pexgol 315 mm (12”), Class 32

Application

Open pit mine dewatering

Lenght

3240 m / 10629 ft

Categories

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Related Case Studies

Линия питьевой воды высокого давления

Линия питьевой воды высокого давления

Компания Antofagasta Minerals, шахта Pelambres
Чили

 | 

2014
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Добыча воды из глубоких скважин (150 м)

Добыча воды из скважин

Шахта Andacollo
Чили

 | 

2015
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023