Skip to content

High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Estudo de Caso Nº

102

Cliente

Lundin Mining
Chile

|

2021

Condições de Trabalho

Flow: 720 m3/h

Solução Pexgol

Pexgol 315 mm (12”), Class 32

Aplicação

Open pit mine dewatering

Comprimento

3240 m / 10629 ft

Categorias

Pexgol Pipe Installation for Open Pit Mine Drainage.

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Estudos de Caso Relacionados

Pexgol pipe was selected for the assembly of a muddy water transport line for a palm oil processing company.

Transport of Muddy Water for Palm Oil Extractor

Extractora Poligrow
Colombia

 | 

2022
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020
Scale build up reduction - highly concentrated lime solution

Process Water – Brine Transportation

SQM Nueva Victoria-Iquique
Chile

 | 

2010