Vertical Drain in Underground Mine

Installation of Pexgol Pipes for Drainage of an Underground Mine

Case Study Nº

67

Customer

Meridian Mine — Faena El Peñón
Chile

|

2018

Working Conditions

Underground work

Pexgol Pipes

Pexgol 160 mm (6”), Class 15 | Pexgol 160 mm (6”), Class 19 | Pexgol 200 mm (8”), Class 26.7

Application

Mine Dewatering

Lenght

800 m

Categories

The Challenge

The Meridian mine (Faena El Peñón) required the installation of a line for the drainage of high-pressure water from the lower level of the mine, passing through the vertical ventilation chimney with a height of 150 meters, continuing through the interior of the mine until an outdoor pool.

Pexgol Solution

The client decided to install 800 m of Pexgol pipes in three di erent sizes:
Pexgol 160 mm (6”) Class 15, 160 mm (6”) Class 19 and 200 mm (8”) Class 26.7.
The installation was very simple:

  • Lifting was carried out in the ventilation chimney.
  • Mechanical connections were used that did not require special tools for installation.
  • In the upper area the pipes were placed on supports provided by the mining company.

Pexgol was selected due to its capabilities:

  • Possibility of supply in long lengths minimizing the connections to only 4.
  • Ability to withstand the drag of more than 5 km from outside to the final assembly point inside the underground mine.
  • Ability to withstand creep involved in vertical mounting of 150 meters.

Related Case Studies

Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Установка дренажной системы на карьере.

Дренажная система

BHP Pampa Norte — Рудник Серро-Колорадо
Чили

 | 

2020
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Транспортировка пульпы бокситовой руды при 95 °C / 203 °F

Алюминиевый завод: Транспортировка рудной пульпы

Уральский алюминиевый завод — «Русал»
Россия

 | 

2013