Cold Water Distribution for External Cooler System

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Case Study Nº

115

Customer

Chip Manufacturer
Israel

|

2022

Working Conditions

Pressure: 6 bars | Temperature: 8°C / 46°F

Pexgol Pipes

Pexgol 355 (14″), 400 (16″) & 630 (24″) mm, Class 15

Application

External Chiller System

Lenght

160 m / 525 ft

Categories

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to increase the capacity of energy in the factory by adding an external chiller system and they needed to finish the installation and implementation as soon as possible.

Pexgol Solution

Due to a successful experience in the past, the company decided to use Pexgol pipes due to the fast installation time, helping to maintain their operation schedule and reduce the total cost of the project.

Related Case Studies

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Транспортировка выщелоченного шлама от очистного сооружения в биологический пруд

Транспортировка спирта для производства рома и бренди

Industria Chiquibul
Гватемала

 | 

2018
Монтаж труб Pexgol для транспортировки рыбы.

Линии разгрузки рыбы

TASA
Перу

 | 

2018

Categories:

Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021