Skip to content

Dry Gas Transportation

Dry Gas Line for Pump Activation.

Case Study Nº

104

Customer

ExxonMobil
Argentina

|

2020

Working Conditions

Maximum pressure: 9 kg / cm2 | Temperature: 25°C | Type of installation: underground

Pexgol Pipes

Pexgol 90 mm (3”) Class 10

Application

Dry gas transportation

Lenght

1880 m / 6168 ft

Categories

The Challenge

ExxonMobil, the unconventional oil field operator located in Neuquén (Argentina), was analyzing the installation of an underground line to convey dry gas. It was used as fuel to drive pumps to transport large volumes of water, used in the development of unconventional deposits.

The company evaluated different pipe alternatives such as: 2-inch diameter carbon steel, or Pexgol cross-linked polyethylene pipe. In addition to the cost, the main premise in the analysis was the reduction of the time of provision and installation of the pipe, which had to be in service in the shortest possible time to supply the needs of the drilling equipment operating in the deposit.

Pexgol Solution

The local team (Argpex) proposed to use a 90 mm diameter Pexgol pipe, class 10 in coils of just under 630 m each. The manufacture and transportation of 1000 km, was carried out in the course of a week.

The uncoiling and unwinding was carried out in a single day with minimal equipment consisting of an uncoiler and a vehicle to pull the pipe, in this case a backhoe. Electrofusion joints were made in one day.

The cost of the Pexgol material, including transportation to the location, represented less than 20% of the cost that a 2-inch carbon steel pipe would have consumed only materials and welding labor. A hydraulic test was carried out and the operation was subsequently started with positive results.

Related Case Studies

Работа с высоким давлением и предельными температурами окружающей среды

Транспортировка воды на медном руднике

Рудник Zaldivar SPA
Чили

 | 

2018
Добыча подземной воды из скважин

Добыча подземных вод

Компания Doña Inés de Collahuasi SCM, шахта Collahuasi
Чили

 | 

2010
Транспортировка спирта концентрацией до 86% для производства рома и бренди

Транспортировка спирта для производства рома и бренди

Cuba Ron
Куба

 | 

2016
Minas Argentinas Replaces HDPE with Pexgol in Its Secondary Leaching Project

Efficient and Safe Irrigation in Secondary Leaching with Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025
Транспортировка воды из скважины с низким pH.

Транспортировка воды на текстильной фабрике

CMT La Laguna
Мексика

 | 

2018
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024