Skip to content

Pexgol Elbow for Slurry Transport

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Case Study Nº

109

Customer

Antioquia Gold
Colombia

|

2022

Working Conditions

Fluid: Sludge | Temperature: 40°C / 104°F

Pexgol Pipes

Pexgol 45° elbow 160 mm, class 15 | GP flanged coupling 160 mm

Application

Slurry transport

Lenght

n/a

Categories

The Challenge

Antioquia Gold, a Colombian mining company, required continuous maintenance to the HDPE pipe (160 mm PN16) that they used for the discharge to the FALCON 1 gravimetric concentrator, which suffered from constant abrasion problems. It had to be thermo-fused in very short sections to give the necessary radius of curvature in the operation. This pipe had a durability of 1 to 2 months maximum.

Pexgol Solution

Due to its durability, ease of installation (mechanical) and because it does not require maintenance, Antioquia Gold decides to use a Pexgol elbow.

The elbow was installed and after 90 days of testing, the elbow and the connections have maintained hermeticity without fluid loss, maintaining the integrity and initial conditions during the period of operation, when subjected to the expected conditions.

Thanks to the benefits of Pexgol elbows and the versatility of the GP flange coupler, the tolerance of the elbow and its easy handling, the operation cuts were carried out satisfactorily. The elbow was installed by simply aligning the mechanical flanges, making the installation complete in 20 minutes.

Related Case Studies

Водоотвод в подземной шахте с уклонами от 40° до 90°.

Отвод воды в подземной шахте

Рудник NEMISA
Мексика

 | 

2018
Транспортировка высококоррозийных материалов от сгустителей на установку нейтрализации

Транспортировка коррозионных материалов

Компания Moa Nickel S.A, Sherritt
Куба

 | 

2015
Прокладка труб из сшитого ПЭ длиной 1000 метров для подземного рудника.

Рудничные дренажные линии

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Транспортирование смешанной жидкости и коррозионных паров (H2S) из осушительных установок

Переработка минерального сырья. Коррозионные жидкости и пар

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2011
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019