Pexgol Elbow for Slurry Transport

Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Case Study Nº

109

Customer

Antioquia Gold
Colombia

|

2022

Working Conditions

Fluid: Sludge | Temperature: 40°C / 104°F

Pexgol Pipes

Pexgol 45° elbow 160 mm, class 15 | GP flanged coupling 160 mm

Application

Slurry transport

Lenght

n/a

Categories

The Challenge

Antioquia Gold, a Colombian mining company, required continuous maintenance to the HDPE pipe (160 mm PN16) that they used for the discharge to the FALCON 1 gravimetric concentrator, which suffered from constant abrasion problems. It had to be thermo-fused in very short sections to give the necessary radius of curvature in the operation. This pipe had a durability of 1 to 2 months maximum.

Pexgol Solution

Due to its durability, ease of installation (mechanical) and because it does not require maintenance, Antioquia Gold decides to use a Pexgol elbow.

The elbow was installed and after 90 days of testing, the elbow and the connections have maintained hermeticity without fluid loss, maintaining the integrity and initial conditions during the period of operation, when subjected to the expected conditions.

Thanks to the benefits of Pexgol elbows and the versatility of the GP flange coupler, the tolerance of the elbow and its easy handling, the operation cuts were carried out satisfactorily. The elbow was installed by simply aligning the mechanical flanges, making the installation complete in 20 minutes.

Related Case Studies

Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Trial Demonstrates Superior Wear Resistance in Sea Water + Ash Slurry Conditions.

Unmatched Durability in Harsh Slurry: Pexgol Outperforms Steel

Tata Power
India

 | 

2023
В аэропорту Гайаны был установлен наружный гидрант и спринклеры внутри помещений

Линия водоснабжения и пожарной воды

Международный аэропорт Cheddi Jagan
Гайана

 | 

2018
Монтаж труб Pexgol на рыбзаводе.

Транспортировка рыбьего жира при 36 °C / 96,8 °F

Компания Guaymas Protein
Мексика

 | 

2018
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Монтаж дренажной системы между скважиной и рудничной дамбой.

Дренирование скважины возле рудничной дамбы

CODELCO — Рудник Эль-Тениенте
Чили

 | 

2019