Replacement of Metal Pipe with PE-X for Formation Water

Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Case Study Nº

116

Customer

Enap Sipetrol Ecuador
Ecuador

|

2022

Working Conditions

Pressure: 25 psi | Temperature: 71°C / 160°F

Pexgol Pipes

Pexgol 225 (8″), Class 24

Application

Formation water transport

Lenght

160 m / 525 ft

Categories

The Challenge

Enap Sipetrol Ecuador, is a branch of the Chilean state oil company Enap.

At their plant, they needed to transport formation water with 65,000-70,000 ppm of sodium chloride, which also had high salinity. This formation water has its origin at the outlet of a three-phase separator, up to a water storage tank. The existing metal pipes in the local market that are used for these processes corrode quickly and present leaks along the way. This situation made it necessary to apply chemical treatment to the pipes, with the cost that this represented, and even so, the treatment did not guarantee the integrity of the pipe.

Pexgol Solution

It was decided to use Pexgol pipe due to the working conditions that it can withstand for these applications and that also has a longer lifespan than the metal pipes usually installed, after the tests carried out, it was satisfactorily observed that it has not been any inconvenience, there are no leaks, no presence of corrosion and no solids adhered.

The installation of the 160 m of 225 mm diameter pipe was carried out with the collaboration of 12 people due to its dimensions and weight, in addition, locally manufactured “cradle” type supports were placed. For the assembly of the pipe, a horizontal unwinding machine was used, a crane truck, mobile roller stations for displacement, mechanical keys, torque meter and manual tools, 4 flanged couplings were installed for the terminations with their respective fixing clamps since that line it was installed in 2 sections.

Related Case Studies

Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
Монтаж труб Pexgol для снабжения питьевой водой со свободным хлором.

Снабжение питьевой водой со свободным хлором

Медицинский центр им. Рабина
Израиль

 | 

2020
Водоотвод в подземной шахте с уклонами от 40° до 90°.

Отвод воды в подземной шахте

Рудник NEMISA
Мексика

 | 

2018
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Осушение сквозных шахтных стволов на подземном свинцово-цинковом руднике.

Осушение сквозных шахтных стволов

Esan Eczacibasi Endustriyel Hammaddeler
Турция

 | 

2019
Монтаж труб Pexgol на рыбзаводе.

Транспортировка рыбьего жира при 36 °C / 96,8 °F

Компания Guaymas Protein
Мексика

 | 

2018