Skip to content

Transporting Brine at High Pressure

Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Case Study Nº

100

Customer

Mekorot
Israel

|

2020

Working Conditions

Pressure: 36 bar | Flow rate: 120 m^3/hr | Chloride concentration: 10,100 mg/l

Pexgol Pipes

Pexgol 250 mm (10”) Class 43

Application

Brine transport at a Borehole

Lenght

300 m / 984 ft

Categories

The Challenge

Mekorot, the national water company of Israel and the country’s top agency for water management, required a corrosion resistant pipe that could hold very high pressure in a deep borehole (300 m). Furthermore, the pipe needed to be able to resist Chloride concentration of 10,100 mg/l.a

Pexgol Solution

A custom-made Pexgol pipe was installed (pipe 250 mm, class 43). The Pexgol pipe was provided in two coils of 150 m each. The two coils were connected by a special coupler that can hold the weight and the high pressure.

The other option that Mekorot considered was a pipe made of super duplex. Since installation of super duplex would take around 3 weeks and cost (approximately) 3,000,000 NIS ($9.3K) while installation of a Pexgol pipe is 3 days and cost about half. Pexgol pipe was the obvious choice.

Related Case Studies

Обеспечение будущего золотодобычи: корпорация Newmont выбирает Pexgol для транспортировки воды

Революция в транспортировке воды компании Newmont с помощью труб Pexgol

Корпорация Newmont
Аргентина

 | 

2018
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Испытательная установка для транспортировки кварцевого песка.

Транспортировка кварцевого песка: сравнение ПЭВП и Pexgol

Covia Corp
Мексика

 | 

2019
Фитинги Pexgol для транспортировки рассола в бразильской химической компании.

Высокая коррозионная стойкость к рассолу

Unipar Carbocloro
Бразилия

 | 

2019
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Монтаж труб Pexgol для транспортировки горячей воды

Горячее водоснабжение

Hilton
Израиль

 | 

2020