Water Transport for Fire Network

Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Case Study Nº

117

Customer

Profertil
Argentina

|

2022

Working Conditions

Pressure: 15 bars | Temperature: Ambient

Pexgol Pipes

Pexgol 180 (6″), 225 (8″) & 280 (12″) mm, Class 15

Application

Water transport for fire network

Lenght

1000 m / 3280 ft

Categories

The Challenge

Profertil, an Argentine company specializing in the manufacture of fertilizers, has a fire network that is more than 10 years old working with carbon steel pipes.

Given that the water they transport has a high chloride content, the lines were affected by corrosion and in many cases even with scale that obstructed the pipe by 50%.

Pexgol Solution

In order to have an efficient fire-fighting network, the Profertil project team opted for a plastic pipe that does not suffer from corrosion, with less possibility of incrustations and its installation does not require specialized machinery.

Likewise, given bad experiences with other types of pipes in relation to installation and operation, the maintenance team carried out pressure tests and resistance to external damage with a sample that was delivered to them.

Finally, 3 lines with Pexgol pipes were installed and it is scheduled in other stages to completely replace the fire network, a total estimate of 7 km.

Electrofusion joints and accessories were used to carry out the derivations and changes of direction.
In relation to other materials and considering that in several places where the pipe had to be buried, obstacles were found from cables and other pipes, the installation was successful.

Related Case Studies

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023
Транспортировка воды c сульфидными и кобальтовыми частицами

Транспортировка воды и сульфидов

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2015
Откачка воды без опор

Откачка воды из карьера

Компания Arcelor Mittal, шахта El Volcan
Мексика

 | 

2017
Прокладка труб из сшитого ПЭ длиной 1000 метров для подземного рудника.

Рудничные дренажные линии

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022