Skip to content

Water Transport with Low pH Level

Transport of acid water at high temperatures

Case Study Nº

2

Customer

Moa Nickel S.A. Sherritt
Cuba

|

2010

Working Conditions

Up to 65°C, 13 bars.

Pexgol Pipes

Pexgol 225 mm, Class 24 (SDR 7.3).

Application

Transportation of Acid Water.

Lenght

2500 m.

Categories

The Challenge

Moa Nickel required to transport a big amount of overflow acid water from the sedimentation tanks to the slurry thickeners plant.

This overflow water substituted the reposition water that the slurry thickeners used.

The client debated regarding the use of a stainless steel pipe SS316L or thermoplastic flexible materials such as HDPE and polyethylene.

Pexgol Solution

At the end, Moa Nickel decided to use Pexgol pipes in long sections, instead of short ones of HDPE and polyethylene, as the best solution for the line, because this type of materials didn’t allow to work under the security standards in the allowable installation time.

The Pexgol pipe was installed in just 8 days with success. The fact that it didn’t require to create a sand bed and the high productivity for its installation in long sections, reduced to the half the installation time for this project. At the end, the client got 25% savings in comparison with the other possible materials.

Related Case Studies

EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Замена трубы ПЭНД на трубу компании Pexgol

Транспортировка суспензии

Шахта Tizapa
Мексика

 | 

2015
Монтаж труб Pexgol на рыбзаводе.

Транспортировка рыбьего жира при 36 °C / 96,8 °F

Компания Guaymas Protein
Мексика

 | 

2018
Монтаж труб Pexgol для системы сжатого воздуха.

Система сжатого воздуха

Типография Rav-Gon
Израиль

 | 

2020
Транспортировка воды через стволы шахт

Откачка воды из карьера

Компания Agnico Eagle, шахта Pinos Altos
Мексика

 | 

2017