Skip to content

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Transformation in the logistics of formation water.

Case Study Nº

158

Customer

Aconcagua Energía
Argentina

|

2023

Working Conditions

Temperature: 35°C / 95°F | Flow: 80 m³/h | Pressure: 10 kg/m

Pexgol Pipes

Pexgol 90 mm class 15 & 110 mm class 24

Application

Injection water transport

Lenght

10,000 m / 32808.4 ft

Categories

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

The Challenge

Aconcagua Energía, a prominent independent energy company in Argentina, faced significant challenges in transporting injection water, crucial for its oil operations. Traditionally, formation water was transported by trucks from the treatment plant to the elevated tanks, which not only represented a high operational cost but also involved risks associated with transport and logistical difficulties, especially during adverse weather conditions or certain times of the year. The need for a more efficient, safe, and economical solution was evident.

The Solution

In search of improving operational efficiency and reducing costs, Aconcagua Energía opted for the implementation of an innovative pipeline using 90 and 110 mm Pexgol for a total of 10,000 meters. The choice of Pexgol was due to its recognized advantages in terms of installation speed, material flexibility, lightness and ease of handling, as well as the ability to transport in rolls, which greatly simplified logistics on the ground.
The installation was carried out in stages, minimizing assembly times and optimizing the resources used. Mechanical double connectors and flanged couplings were used, facilitating a safe and efficient integration into the existing system.

The project not only eliminated the dependency on truck transportation but also brought tangible benefits in terms of operational costs and associated risks. The first phase of the installation included the assistance and training of Argpex in unrolling techniques and the use of mechanical connectors. For the later stages, the Aconcagua Energía team was able to carry out the installation autonomously, demonstrating the effectiveness and ease of implementation of the Pexgol system.

Related Case Studies

Монтаж труб Pexgol на всасывающей линии для транспортировки горячей абразивной рассольной пульпы.

Обработка горячего и абразивного калийного рассола

Компания по производству удобрений
Канада

 | 

2017
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
A solution designed to operate safely and reliably under high temperatures and demanding installation conditions.

A Flexible Solution for Formation Water UnderDemanding Conditions

Pluspetrol
Argentina

 | 

2026
Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Прокладка труб из сшитого ПЭ длиной 3000 метров для подземного рудника.

Дренажные линии в подземном руднике

Lundin Mining — Рудник Канделария-Норте
Чили

 | 

2020
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023