Skip to content

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Transformation in the logistics of formation water.

Case Study Nº

158

Customer

Aconcagua Energía
Argentina

|

2023

Working Conditions

Temperature: 35°C / 95°F | Flow: 80 m³/h | Pressure: 10 kg/m

Pexgol Pipes

Pexgol 90 mm class 15 & 110 mm class 24

Application

Injection water transport

Lenght

10,000 m / 32808.4 ft

Categories

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

The Challenge

Aconcagua Energía, a prominent independent energy company in Argentina, faced significant challenges in transporting injection water, crucial for its oil operations. Traditionally, formation water was transported by trucks from the treatment plant to the elevated tanks, which not only represented a high operational cost but also involved risks associated with transport and logistical difficulties, especially during adverse weather conditions or certain times of the year. The need for a more efficient, safe, and economical solution was evident.

The Solution

In search of improving operational efficiency and reducing costs, Aconcagua Energía opted for the implementation of an innovative pipeline using 90 and 110 mm Pexgol for a total of 10,000 meters. The choice of Pexgol was due to its recognized advantages in terms of installation speed, material flexibility, lightness and ease of handling, as well as the ability to transport in rolls, which greatly simplified logistics on the ground.
The installation was carried out in stages, minimizing assembly times and optimizing the resources used. Mechanical double connectors and flanged couplings were used, facilitating a safe and efficient integration into the existing system.

The project not only eliminated the dependency on truck transportation but also brought tangible benefits in terms of operational costs and associated risks. The first phase of the installation included the assistance and training of Argpex in unrolling techniques and the use of mechanical connectors. For the later stages, the Aconcagua Energía team was able to carry out the installation autonomously, demonstrating the effectiveness and ease of implementation of the Pexgol system.

Related Case Studies

Замена трубы ПЭНД на трубу компании Pexgol

Транспортировка сжатого воздуха

Шахта компании Saucito S.A. de C.V.
Мексика

 | 

2017
Монтаж дренажной системы между скважиной и рудничной дамбой.

Дренирование скважины возле рудничной дамбы

CODELCO — Рудник Эль-Тениенте
Чили

 | 

2019
Обустройство скважины с секционным монтажом труб в ограниченном пространстве.

Обустройство водозаборной скважины в ограниченном пространстве

Mekorot
Израиль

 | 

2020
Прокладка подземных труб для транспортировки воды по дороге рудника.

Транспортировка воды по дороге рудника

CODELCO — Рудник Андина
Чили

 | 

2019
Транспортировка грязной воды (жидкие отходы производства пальмового масла) с высоким содержанием органических веществ.

Транспортировка грязной воды на заводе по переработке пальмового масла

La Gloria
Колумбия

 | 

2020
Water line feed from wells to mine

Water Lines — High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012