Skip to content

Vertical Solution for Mine Dewatering in Fresnillo

A Challenging Project That Eliminated Booster Stations Thanks to Pexgol’s Flexibility.

Case Study Nº

179

Customer

Fresnillo
Mexico

|

2025

Working Conditions

Temperature: 30°C / 86°F | Flow Rate: 120 m³/hour | Pressure: 224 psi | Fluid Components: Mine water

Pexgol Pipes

Pexgol 6″, SDR 9

Application

Underground mine dewatering

Lenght

Two coils of 150 meters each (Total: 300 m / 984 ft)

Categories

Vertical Solution for Mine Dewatering in Fresnillo

The Challenge

Minera Fresnillo Plc, the world’s largest silver producer and one of Mexico’s top gold producers, faced a new challenge in its underground operation at the San Alberto Ramp. It was necessary to pump mine water from level -695 to level -610, where infrastructure already existed to convey the water to the surface.

Traditional solutions involved installing conventional piping along horizontal tunnels, which meant greater distances, higher energy consumption, and the need for intermediate booster stations. Additionally, the environmental conditions—temperatures up to 32°C and 100% relative humidity—added complexity to the project.

The Solution

Thanks to the unique properties of Pexgol 6” SDR9 pipe, a direct vertical installation of 130 meters (426 ft) elevation difference was implemented through two 10-inch boreholes, without requiring perfect borehole alignment. The system’s flexibility andmechanical strength allowed it to adapt precisely to the borehole conditions.

The installation was executed with a single submersible pump located at level -695, which pushed the water directly to level -610, completely eliminating the need for intermediate booster stations. Main accessories included flanged couplings and load clamps.

Despite high humidity and limited tunnel space, the installation of both lines was completed in just 10 effective hours. The pipes were unrolled and inserted simultaneously into the inclined borehole without compromising personnel safety.

A key factor in the project’s success was the technical support provided by the Pexgol team. Given the lack of prior experience with vertical installations, training sessions and planning meetings were conducted weeks in advance, ensuring the crew was fully prepared and confident to carry out the installation

Related Case Studies

Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Трубы Pexgol для транспортировки сточных вод при температуре 30 °C / 86 °F в подземном руднике.

Перекачка сточных вод от горных работ

AngloGold Ashanti
Бразилия

 | 

2019
Транспортировка подземных вод с низким уровнем pH

Транспортировка подземных вод

Компания Grupo México, шахта Buena Vista del Cobre
Мексика

 | 

2015
Установка труб на горе

Транспортировка талых стоков

Компания Codelco Andina, проект TADA 1-2
Чили

 | 

2013
Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023