Skip to content

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Case Study Nº

130

Customer

Nexa Resources
Brazil

|

2023

Working Conditions

Temperature: 25° — 38°C (77° — 100.4°F) | Flow rate: 190 — 260 m3/h | Pressure: 8 to 12 bar | Components: 18-25% cw — Density 1.18 | Critical speed 1 m/s

Pexgol Pipes

Pexgol 225 mm (3″), Class 15

Application

Zinc Slurry Transportation

Lenght

1240 m / 4068 ft

Categories

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

The Challenge

Nexa Resources, a global mining and metallurgy leader, was seeking innovative ways to reduce the environmental impact of its Tres Marias mining unit, located in Bello Horizonte, Brazil.

An integral part of this plan involved a significant adjustment to their waste management strategy. The team aimed to eliminate the existing tailings dam by transporting a mixture of dam water and pulp to a filtration plant. Here, the water was to be separated and reused, and the pulp transported to a drying plant for repurposing. However, the transition necessitated a reliable, resilient, and efficient piping system that could support the transportation of pulp—a zinc hydrometallurgy waste—over a distance of approximately 1240 meters (or about 4068 feet).

Pexgol Solution

Pexgol was chosen as the ideal solution for this challenging operation. Two pipe dimensions—Pexgol 180 mm and Pexgol 250 mm, class 15—were provided in coils ranging from 200 to 300 meters (approximately 656 to 984 feet) each. These pipes proved perfect for the task at hand, with a fluid temperature tolerance between 25-38°C (77-100.4°F), a flow rate of 190 — 260 m³-h, and pressure between 8 to 12 bar.
Pexgol’s advantages—fast installation and provision of longer lengths—made it an optimal choice for Nexa Resources.

Though initially, there were complications with the electrofusion connections due to the contractor’s unfamiliarity with the process, the Pexgol technical team’s support enabled successful completion of the task. The pipe ends were placed at “registry points” to monitor their operational efficiency, further ensuring a smooth and successful transition.

Pexgol’s solution effectively supported Nexa Resource’s commitment to sustainable mining, providing a reliable, efficient, and durable pipeline for their new waste management process.

Related Case Studies

Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Монтаж труб Pexgol для транспортировки пластовой воды (с газом и минералами)

Газовые скважины: обработка пластовой воды

Canacol
Колумбия

 | 

2018
600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

Kimex
Mexico

 | 

2025
Горячий сильвинитовый насыщенный рассол с температурой 114 °C (237 °F)

Переработка минерального сырья — установка по переработке углекислого калия

ICL group, работы на Мертвом море
Израиль

 | 

1987
Монтаж труб Pexgol для снабжения питьевой водой со свободным хлором.

Снабжение питьевой водой со свободным хлором

Медицинский центр им. Рабина
Израиль

 | 

2020
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018