Facing the Challenges of the Neuquén Terrain in Argentina

Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Case Study Nº

145

Customer

Pluspetrol
Argentina

|

2023

Working Conditions

Temperature: 20°C / 68°F | Pressure: 10 bars | Flow: 30m3/h | Components: River water

Pexgol Pipes

Pexgol 110 & 160 mm, class 15

Application

Water transport

Lenght

13300 m / 43773 ft

Categories

Facing the Challenges of the Neuquén Terrain in Argentina

The Challenge

Pluspetrol and JMAC Resources, both giants in their respective domains, embarked on Yacimiento La Caleta in Neuquén, Argentina, with a mission. The objective was clear: to install an aerial pipeline that would last for a year and withstand both pressure and weather conditions. Without an existing line for this project, they faced the challenge of erecting a robust but temporary water transport system, ensuring it could handle the demands of transporting river water at 20°C (68°F) and a pressure of 10 bars.

Pexgol Solution

To address this formidable challenge, the Pexgol 110-160 mm, class 15 pipeline emerged as the ideal solution. Spanning a vast length of 13,330 meters (43,773 feet), this pipeline offered the benefits of quick installation, lightweight handling, and extended sections.

Not only was the installation process streamlined to just one week using the unroller provided by Argpex, but on-site training was also given to JMAC for Pluspetrol. This ensured expert handling of Pexgol’s mechanical joints and a seamless integration process. The testament to its success was not only the efficient water transport but also the excellent after-sales service, reinforcing the brand’s commitment to quality and customer satisfaction.

Related Case Studies

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Монтаж труб Pexgol для вертикального дренажа

Вертикальный отвод вод

Полтавский ГОК, Ferrexpo
Украина

 | 

2019
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Испытание: трубы Pexgol и трубы ПЭНД для транспортировки рассола

Трубы Pexgol в сравнении с трубами ПЭНД для транспортировки рассола

Компания YBL
Боливия

 | 

2017