Skip to content

Facing the Challenges of the Neuquén Terrain in Argentina

Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Estudo de Caso Nº

145

Cliente

Pluspetrol
Argentina

|

2023

Condições de Trabalho

Temperature: 20°C / 68°F | Pressure: 10 bars | Flow: 30m3/h | Components: River water

Solução Pexgol

Pexgol 110 & 160 mm, class 15

Aplicação

Water transport

Comprimento

13300 m / 43773 ft

Categorias

Facing the Challenges of the Neuquén Terrain in Argentina

The Challenge

Pluspetrol and JMAC Resources, both giants in their respective domains, embarked on Yacimiento La Caleta in Neuquén, Argentina, with a mission. The objective was clear: to install an aerial pipeline that would last for a year and withstand both pressure and weather conditions. Without an existing line for this project, they faced the challenge of erecting a robust but temporary water transport system, ensuring it could handle the demands of transporting river water at 20°C (68°F) and a pressure of 10 bars.

Pexgol Solution

To address this formidable challenge, the Pexgol 110-160 mm, class 15 pipeline emerged as the ideal solution. Spanning a vast length of 13,330 meters (43,773 feet), this pipeline offered the benefits of quick installation, lightweight handling, and extended sections.

Not only was the installation process streamlined to just one week using the unroller provided by Argpex, but on-site training was also given to JMAC for Pluspetrol. This ensured expert handling of Pexgol’s mechanical joints and a seamless integration process. The testament to its success was not only the efficient water transport but also the excellent after-sales service, reinforcing the brand’s commitment to quality and customer satisfaction.

Estudos de Caso Relacionados

Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012

Categorias:

The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023