Facing the Challenges of the Neuquén Terrain in Argentina

Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Estudo de Caso Nº

145

Cliente

Pluspetrol
Argentina

|

2023

Condições de Trabalho

Temperature: 20°C / 68°F | Pressure: 10 bars | Flow: 30m3/h | Components: River water

Solução Pexgol

Pexgol 110 & 160 mm, class 15

Aplicação

Water transport

Comprimento

13300 m / 43773 ft

Categorias

Facing the Challenges of the Neuquén Terrain in Argentina

The Challenge

Pluspetrol and JMAC Resources, both giants in their respective domains, embarked on Yacimiento La Caleta in Neuquén, Argentina, with a mission. The objective was clear: to install an aerial pipeline that would last for a year and withstand both pressure and weather conditions. Without an existing line for this project, they faced the challenge of erecting a robust but temporary water transport system, ensuring it could handle the demands of transporting river water at 20°C (68°F) and a pressure of 10 bars.

Pexgol Solution

To address this formidable challenge, the Pexgol 110-160 mm, class 15 pipeline emerged as the ideal solution. Spanning a vast length of 13,330 meters (43,773 feet), this pipeline offered the benefits of quick installation, lightweight handling, and extended sections.

Not only was the installation process streamlined to just one week using the unroller provided by Argpex, but on-site training was also given to JMAC for Pluspetrol. This ensured expert handling of Pexgol’s mechanical joints and a seamless integration process. The testament to its success was not only the efficient water transport but also the excellent after-sales service, reinforcing the brand’s commitment to quality and customer satisfaction.

Estudos de Caso Relacionados

Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Transportation of Bauxite Ore Slurry at 95°C / 203°F

Alumina Plant: Ore Slurry Transportation

Urals Alumina Plant – Rusal
Russia

 | 

2013
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021