High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Case Study Nº

102

Customer

Lundin Mining
Chile

|

2021

Working Conditions

Flow: 720 m3/h

Pexgol Pipes

Pexgol 315 mm (12”), Class 32

Application

Open pit mine dewatering

Lenght

3240 m / 10629 ft

Categories

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Related Case Studies

How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024
Испытательная установка для транспортировки кварцевого песка.

Транспортировка кварцевого песка: сравнение ПЭВП и Pexgol

Covia Corp
Мексика

 | 

2019
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Транспортировка воды c сульфидными и кобальтовыми частицами

Транспортировка воды и сульфидов

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2015
Транспортировки суспензии с высоким содержанием никеля

Транспортировка выщелоченной суспензии

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2013