High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Case Study Nº

102

Customer

Lundin Mining
Chile

|

2021

Working Conditions

Flow: 720 m3/h

Pexgol Pipes

Pexgol 315 mm (12”), Class 32

Application

Open pit mine dewatering

Lenght

3240 m / 10629 ft

Categories

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Related Case Studies

The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
EMESA Optimizes Formation Water Transportation in Mendoza.

Pexgol’s Solution in Secondary Recovery for EMESA

EMESA
Argentina

 | 

2023
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Greater operational efficiency with fewer joints and fast implementation.

Fresh Water Line Optimization in an Oil Field in Argentina

Phoenix Global Resources
Argentina

 | 

2025
Minas Argentinas Replaces HDPE with Pexgol in Its Secondary Leaching Project

Efficient and Safe Irrigation in Secondary Leaching with Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025
The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022