Navigating extreme conditions with Pexgol’s PE-X pipes

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Case Study Nº

151

Customer

Anglo American Perú
Peru

|

2023

Working Conditions

Temperature: 15°-20°C (59° — 68°F) | Flow: 450 m^3/h | Pressure: 22 bar | Fluid components: Tailings with high percentage of solids 70%CW

Pexgol Pipes

Pexgol 14″, SDR 11

Application

Tailings transportation in copper mining

Lenght

180 m / 590 ft

Categories

Navigating extreme conditions with Pexgol’s PE-X pipes

The Challenge

In 2023, Anglo American Peru, a global mining leader, faced a significant challenge at its Quellaveco mine. The existing HDPE pipeline, designed for transporting copper tailings with high solids (70%CW) at a temperature of 15-20°C (59-68°F), a flow rate of 450 m³/hr, and a pressure of 22 bar, required an urgent upgrade. The pipeline needed to be rapidly installed on a steep slope with a 60-meter (197-foot) drop, to enhance the capacity of the concentrator plant and integrate cyclones into the system.

Pexgol Solution

The 14-inch PE-X pipes from Pexgol, with a total length of 180 meters in two segments of 90 meters each, were the chosen solution. Using Pexgol fittings like Electrofusion Couplers, Stub Ends, and Support Bridges, the installation was completed in approximately 7 days by a specialized team. The process involved a Pexgol vertical uncoiler and two cranes, ensuring a quick and efficient setup. The critical benefits of the Pexgol piping system, such as quick installation, high chemical and corrosion resistance, lightweight handling, and long lengths, were key to making it ideal for the project.

Related Case Studies

Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Монтаж линии Pexgol на глубине 200 метров в подземном руднике

Транспортировка сжатого воздуха

Рудник Meridian — Faena El Peñón
Чили

 | 

2018
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Монтаж дренажной системы между скважиной и рудничной дамбой.

Дренирование скважины возле рудничной дамбы

CODELCO — Рудник Эль-Тениенте
Чили

 | 

2019
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024