Skip to content

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Case Study Nº

187

Customer

Endeavour Silver
Mexico

|

2024

Working Conditions

Temperature: Ambient (pipeline exposed to direct sunlight) | Flow Rates: 1.4 m³/h – Tailings (6” SDR 7.3) 107 m³/h – Recovered water (8” SDR 4.5) 5.5 m³/h – Concentrate (50 mm SDR 11) | Pressure: 24 bar static pressure – Tailings line 32.3 bar – Recovered water line Free discharge – Remaining lines

Pexgol Pipes

Pexgol 2”, 3”, 4”, 6” y 8”

Application

Tailings (50% solids) | Concentrate | Recovered water (ascending pumped line) | Raw water | Potable water | Fire protection system water

Lenght

4 lines of 2,400 m each 1 line of 3,300 m

Categories

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

The Challenge

Endeavour Silver’s Terronera Mine required the design and implementation of a completely new hydraulic system, as no existing infrastructure was available on site. The project involved transporting fluids over an elevation difference exceeding 300 meters, generating high velocities and varying pressure levels along the route. These demanding hydraulic conditions posed significant operational risks, including:

  • Increased abrasion and wear
  • Vibrations within the piping system
  • Higher probability of premature failures
  • Construction challenges across steep slopes and uneven terrain

Additionally, the recovered water line operated in an ascending configuration using pumping systems, while the remaining lines functioned by gravity. This required a versatile piping solution capable of adapting to different operating regimes while maintaining long-term reliability.

The Solution

To meet the project’s technical requirements, a Pexgol piping system was selected due to its unique combination of mechanical strength, hydraulic efficiency, and installation flexibility.
The solution successfully addressed the complex routing conditions and demanding operating parameters.
Key Advantages of the Pexgol System:

  • Fast installation, reducing construction time
  • Flexible and lightweight pipes, ideal for complex topography
  • Supplied in long coils, minimizing joints and potential failure points
  • Excellent abrasion resistance for tailings and concentrate transport
  • High pressure resistance for static pressures exceeding 30 bar
  • UV resistance for exposed installations
  • Long service life in demanding mining environments

During execution, design modifications were required as the project progressed into more challenging construction stages. The inherent flexibility of the Pexgol system, combined with technical support from the engineering team, allowed efficient adaptation to new field conditions.
Results Achieved:

  • Continuity of installation activities
  • Reduced construction risks
  • Optimal compatibility between material performance and real operating conditions
  • Compliance with performance, safety and reliability criteria

Related Case Studies

Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Монтаж труб Pexgol для транспортировки хвостов, образующихся при горной добыче.

Транспортировка хвостов с 50% содержанием твердых частиц

Golden Resource Corp. — Золотой рудник Дон Дэвид
Мексика

 | 

2019
Монтаж труб Pexgol для транспортировки пластовой воды (с газом и минералами)

Газовые скважины: обработка пластовой воды

Canacol
Колумбия

 | 

2018
Монтаж дренажной системы между дамбами на медном руднике.

Транспортировка воды между дамбами

CODELCO — Рудник Эль-Тениенте
Чили

 | 

2019
Отвод воды из шахты

Отвод воды из шахты

Компания El Peñón Yamana Gold, шахта Meridian
Чили

 | 

2016
The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022