Pexgol: Significant Pipe Wall Scale Reduction

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Case Study Nº

137

Customer

Copper Mine
USA

|

2022

Working Conditions

Temperature: Ambient | Flow: 60 gpm — 6ft/s | Pressure: 20 psi

Pexgol Pipes

Application

Pilot Study: Scaling performance comparison between same sized Pexgol & HDPE pipes

Lenght

304 m / 1,000 ft

Categories

The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Introduction

A prominent copper mine in Arizona that uses an in-situ copper ore recovery process, experienced scaling issues in the existing HDPE (PE 4710) piping deployed in the rinse cycle phase of ore extraction.
Scaling in the HDPE pipes caused clogging and despite the use of scale inhibitors and cleaning, some pipes were still being replaced too frequently.

The Problem

Increased operational maintenance and reduced efficiency of the HDPE pipes
created the need for a more efficient, long-term solution.

Pexgol Solution

Pexgol was proposed as the solution for reduced scaling.
A controlled pilot study was commissioned by the mine to compare gypsum slurry pumped through Pexgol vs HDPE (PE 4710) for a period of 4 weeks.
Various flow velocities, pressures and ambient temperatures were monitored and compared after 2 and 4 weeks.

Results

The Pexgol pipes showed almost no scaling compared with the scaled HDPE pipes after 2 and 4 weeks.
It was recommended that Pexgol replace HDPE at the rinse cycle phase of ore extraction of the mine.

Conclusion

Pexgol pipes are a viable solution for similar slurry applications.

Related Case Studies

Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Транспортирование смешанной жидкости и коррозионных паров (H2S) из осушительных установок

Переработка минерального сырья. Коррозионные жидкости и пар

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2011
Осушение шахты в условиях высокого давления

Осушение шахты — в условиях высокого давления

Antofagasta Minerals, шахта «Михилья»
Чили

 | 

2011
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Монтаж труб Pexgol на установке подготовки пластовой воды.

Установка водоподготовки для вторичной закачки

YPF
Аргентина

 | 

2020