Skip to content

Water Transport on Crossroads

Transportation of water in more than 150 mining crossroads

Case Study Nº

26

Customer

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

|

2012

Working Conditions

Extreme environmental temperatures (-25°C to 40°C), 10 bars.

Pexgol Pipes

Pexgol 160 mm, Class 15 (SDR 11).

Application

Water transport.

Lenght

4000 m.

Categories

Transportation of water in more than 150 mining crossroads

The Challenge

Collahuasi Mine required to transport water that needed to cross mining crossroads, where the pipes where continuously exposed by the heavy trucks that circulate the area.

In the past, the client used HDPE pipes that created a bottleneck on the crossroads. To gain time they reinforced them with steel pipes that acted as steel protectors for the pipes. But still, the solution was very expensive.

Pexgol Solution

Since 2012 the client decided to replace all the water HDPE pipes with Pexgol. This change brought several benefits to the company, such us better productivity during the installation of the lines, better performance under harsh conditions, and thanks to its mechanical properties it improved the issues reducing the bottleneck on the crossroads.

The average installation time was reduced from 3-4 days to 4 hours per crossroad. On each one a Pexgol pipe was installed without a sand bed neither a steel protector. It only required a trench and a simple process to compact ground, using the natural field.

Related Case Studies

Installation of Pexgol Pipes for a Free Chlorine Potable Water Supply.

Free Chlorine Potable Water Supply

Rabin Medical Center
Israel

 | 

2020
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021
Pexgol extends pipe lifespan and reduces maintenance in salt production.

Fewer Shutdowns, Greater Efficiency: Pexgol in the Salt Industry

Sales del Istmo
Mexico

 | 

2023
Dalvian SA Implements Pexgol for Potable Water Pipeline in the Mountains.

Innovative Solution for Water Supply in Extreme Terrain

Dalvian
Argentina

 | 

2024