Open Cast Mine Dewatering
Dewatering without Supports
Case Study Nº
37
Customer
El Volcan Mine Arcelor Mittal
Mexico
|
2017
Working Conditions
Pressure 189 psi; height difference 130 m; solids 15-20 %; fluid temperature 20-25°C.
Pexgol Pipes
Pexgol Class 15 160 x 14.6.
Application
Dewatering
Lenght
650 meters.
Categories

The Challenge
El Volcan Mine was facing a excess water that required dewatering. During rainy season the Mine area suffers from constant floods due to high level groundwater that wasn’t taken under consideration.
In addition, the client was looking for a quick and easy to install solution, since the pipe was going to be suspended, and a regular pipe will require supports.
Pexgol Solution
El Volcan Mine decided to replace their current 6” RD11 HDPE pipe for a Pexgol class 15 pipe 160 x 14.6 due to it quick and easy installation.
650 meters of Pexgol pipe was provided. The installation was done in a quick and efficient way, and count with Pexgol technical support during the whole process.
Related Case Studies
Efficiency and Durability in Handling Muddy Water
Industrial Aceitera del Casanare
Colombia
|
2023
Transport of Compressed Air
Meridian Mine – Faena El Peñón
Chile
|
2018
Open Cast Mine Dewatering
Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile
|
2013
Addressing Drainage Challenges with Pexgol
Avino Mine
Mexico
|
2023
Water Transport Between Dams
CODELCO – El Teniente Mine
Chile
|
2019