Open Cast Mine Dewatering
Dewatering without Supports
Estudo de Caso Nº
37
Cliente
El Volcan Mine Arcelor Mittal
Mexico
|
2017
Condições de Trabalho
Pressure 189 psi; height difference 130 m; solids 15-20 %; fluid temperature 20-25°C.
Solução Pexgol
Pexgol Class 15 160 x 14.6.
Aplicação
Dewatering
Comprimento
650 meters.
Categorias
The Challenge
El Volcan Mine was facing a excess water that required dewatering. During rainy season the Mine area suffers from constant floods due to high level groundwater that wasn’t taken under consideration.
In addition, the client was looking for a quick and easy to install solution, since the pipe was going to be suspended, and a regular pipe will require supports.
Pexgol Solution
El Volcan Mine decided to replace their current 6” RD11 HDPE pipe for a Pexgol class 15 pipe 160 x 14.6 due to it quick and easy installation.
650 meters of Pexgol pipe was provided. The installation was done in a quick and efficient way, and count with Pexgol technical support during the whole process.
Estudos de Caso Relacionados
Dewatering Through Shafts
Esan Eczacibasi Endustriyel Hammaddeler
Turkey
|
2019
Mining Drainage Lines
Lundin Mining – Alcaparosa Mine
Chile
|
2019
Drainage System
BHP Pampa Norte – Cerro Colorado Mine
Chile
|
2020
High Corrosion Resistance Against Brine
Unipar Carbocloro
Brazil
|
2019