Open Cast Mine Dewatering

Dewatering without Supports

Estudo de Caso Nº

37

Cliente

El Volcan Mine Arcelor Mittal
Mexico

|

2017

Condições de Trabalho

Pressure 189 psi; height difference 130 m; solids 15-20 %; fluid temperature 20-25°C.

Solução Pexgol

Pexgol Class 15 160 x 14.6.

Aplicação

Dewatering

Comprimento

650 meters.

Categorias

Dewatering without Supports

The Challenge

El Volcan Mine was facing a excess water that required dewatering. During rainy season the Mine area suffers from constant floods due to high level groundwater that wasn’t taken under consideration.

In addition, the client was looking for a quick and easy to install solution, since the pipe was going to be suspended, and a regular pipe will require supports.

Pexgol Solution

El Volcan Mine decided to replace their current 6” RD11 HDPE pipe for a Pexgol class 15 pipe 160 x 14.6 due to it quick and easy installation.

650 meters of Pexgol pipe was provided. The installation was done in a quick and efficient way, and count with Pexgol technical support during the whole process.

Estudos de Caso Relacionados

Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019