Open Cast Mine Dewatering

Dewatering without Supports

Estudo de Caso Nº

37

Cliente

El Volcan Mine Arcelor Mittal
Mexico

|

2017

Condições de Trabalho

Pressure 189 psi; height difference 130 m; solids 15-20 %; fluid temperature 20-25°C.

Solução Pexgol

Pexgol Class 15 160 x 14.6.

Aplicação

Dewatering

Comprimento

650 meters.

Categorias

Dewatering without Supports

The Challenge

El Volcan Mine was facing a excess water that required dewatering. During rainy season the Mine area suffers from constant floods due to high level groundwater that wasn’t taken under consideration.

In addition, the client was looking for a quick and easy to install solution, since the pipe was going to be suspended, and a regular pipe will require supports.

Pexgol Solution

El Volcan Mine decided to replace their current 6” RD11 HDPE pipe for a Pexgol class 15 pipe 160 x 14.6 due to it quick and easy installation.

650 meters of Pexgol pipe was provided. The installation was done in a quick and efficient way, and count with Pexgol technical support during the whole process.

Estudos de Caso Relacionados

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categorias: