Skip to content

Carriage of Chemicals at Sea Port

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Case Study Nº

50

Customer

Ashdod Sea Port
Israel

|

2016

Working Conditions

High pressure, abrasion, constant water hammers

Pexgol Pipes

Pexgol 315 mm 90 Class 12 SDR 16.3

Application

Chemicals Transportation

Lenght

1.3 km

Categories

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

The Challenge

Commonly at Ashdod Sea Port (Israel) they require to transport all kinds of chemicals, acids and slurries to ship for export, from the port to the shipping boats.

In order to fulfill this procedure they installed cast steel pipes, which suffer from corrosion inside the pipe due to the chemicals after so many years carrying them. This steel pipes were very expensive to maintain, including frequent cleaning.

Pexgol Solution

An engineering firm specializing in the chemical industry, stated that Pexgol was the ideal solution for dealing with the challenges of the
line:

  • Pexgol’s proven ability to deal with acids.
  • Durability of the pipes.
  • The possibility of installing a 315 mm continuous pipe line without flanged connections in curved sections, saving the number of flanges and dramatically reducing weak points.

The Pexgol pipes were installed hanging with fixpoints on top of the current steel pipes, without damaging them. Omegas were installed as well (that couldn’t be done with PE pipes).
Took 10 days to install and operate the line, having the ships waiting in the water, the line started working immediately after completion.

Related Case Studies

Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011