Carriage of Chemicals at Sea Port

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Estudo de Caso Nº

50

Cliente

Ashdod Sea Port
Israel

|

2016

Condições de Trabalho

High pressure, abrasion, constant water hammers

Solução Pexgol

Pexgol 315 mm 90 Class 12 SDR 16.3

Aplicação

Chemicals Transportation

Comprimento

1.3 km

Categorias

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

The Challenge

Commonly at Ashdod Sea Port (Israel) they require to transport all kinds of chemicals, acids and slurries to ship for export, from the port to the shipping boats.

In order to fulfill this procedure they installed cast steel pipes, which suffer from corrosion inside the pipe due to the chemicals after so many years carrying them. This steel pipes were very expensive to maintain, including frequent cleaning.

Pexgol Solution

An engineering firm specializing in the chemical industry, stated that Pexgol was the ideal solution for dealing with the challenges of the
line:

  • Pexgol’s proven ability to deal with acids.
  • Durability of the pipes.
  • The possibility of installing a 315 mm continuous pipe line without flanged connections in curved sections, saving the number of flanges and dramatically reducing weak points.

The Pexgol pipes were installed hanging with fixpoints on top of the current steel pipes, without damaging them. Omegas were installed as well (that couldn’t be done with PE pipes).
Took 10 days to install and operate the line, having the ships waiting in the water, the line started working immediately after completion.

Estudos de Caso Relacionados

Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Water line feed from wells to mine

Mine Dewatering – High Pressure Conditions

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011
A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Scaling Up Efficiency: District Energy at Penn State Harrisburg

Penn State University - Harrisburg
USA

 | 

2021
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024