Installation of Pexgol Pipes for Drainage in a Vertical Ground

Case Study Nº

69

Customer

Ferrexpo Poltava Mining
Ukraine

|

2019

Working Conditions

Vertical installation | Ambient temperature: -30°C to 40°C / -22°F to 104°F

Pexgol Pipes

Pexgol 315 mm (12”), class 30 | Pexgol 315 mm (12”), class 24 | Pexgol 315 mm (12”), class 19 | Pexgol 280 mm (10”), class 10

Application

Mine Dewatering

Lenght

2700 m

Categories

Installation of Pexgol Pipes for Drainage in a Vertical Ground

The Challenge

Ferrexpo Poltava Mining required the installation of pipeline for mine dewatering to be installed vertically from the bottom of the quarry to its surface. The pipe needed to be resistant to cracks and be provided in long sections in order to avoid many joints.

Pexgol Solution

The client decided to install Pexgol pipes with OD 315 mm (12”) with 30, 24 and 19 class in coils by 90 and 120 m each for most difficult areas where the pressure varied from 32 to 15 bars. At the end of the line Pexgol OD 280 mm (10”), class 10 pipes were used in straight sections of 11.8 m.
All the pipes were connected by electrofusion couplers. In the places with high pressure were also used reinforcements for a safe installation.

A Caterpillar D10T bulldozer and the 40 ton excavator was used for unwinding the coils on core. Then the pipe were dropped from the top by the bulldozer & excavator. All connections were made with the electrofusion couplers. In the most difficult areas were also used reinforcements and fixpoint bridges.

Related Case Studies

Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022