Skip to content

Vertical Dewatering

Installation of Pexgol Pipes for Drainage in a Vertical Ground

Case Study Nº

69

Customer

Ferrexpo Poltava Mining
Ukraine

|

2019

Working Conditions

Vertical installation | Ambient temperature: -30°C to 40°C / -22°F to 104°F

Pexgol Pipes

Pexgol 315 mm (12”), class 30 | Pexgol 315 mm (12”), class 24 | Pexgol 315 mm (12”), class 19 | Pexgol 280 mm (10”), class 10

Application

Mine Dewatering

Lenght

2700 m

Categories

Installation of Pexgol Pipes for Drainage in a Vertical Ground

The Challenge

Ferrexpo Poltava Mining required the installation of pipeline for mine dewatering to be installed vertically from the bottom of the quarry to its surface. The pipe needed to be resistant to cracks and be provided in long sections in order to avoid many joints.

Pexgol Solution

The client decided to install Pexgol pipes with OD 315 mm (12”) with 30, 24 and 19 class in coils by 90 and 120 m each for most difficult areas where the pressure varied from 32 to 15 bars. At the end of the line Pexgol OD 280 mm (10”), class 10 pipes were used in straight sections of 11.8 m.
All the pipes were connected by electrofusion couplers. In the places with high pressure were also used reinforcements for a safe installation.

A Caterpillar D10T bulldozer and the 40 ton excavator was used for unwinding the coils on core. Then the pipe were dropped from the top by the bulldozer & excavator. All connections were made with the electrofusion couplers. In the most difficult areas were also used reinforcements and fixpoint bridges.

Related Case Studies

In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
Field evaluation of Pexgol PE-Xa pipes under highly abrasive iron ore slurry conditions at Cauê Mine.

Test Case – Field Performance Evaluation of Pexgol

Vale
Brazil

 | 

2025
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Dewatering tThrough Shafts for an Underground Lead-Zinc Mine.

Dewatering Through Shafts

Esan Eczacibasi Endustriyel Hammaddeler
Turkey

 | 

2019