Skip to content

Installation of Water Well in Reduced Space

Installation of a Borehole with Pipe in Sections for Reduced Space.

Case Study Nº

95

Customer

Mekorot
Israel

|

2020

Working Conditions

Pressure: 10 bar

Pexgol Pipes

Pexgol 200 mm (6”), class 24

Application

Borehole for treated effluent water

Lenght

70 m

Categories

Installation of a Borehole with Pipe in Sections for Reduced Space.

The Challenge

Mekorot, the national company in charge of water supply in Israel, among other activities, has installed and used Pexgol pipes for water wells for more than 30 years.

The wells were always installed using one of Pexgol’s great advantages, which is the possibility of supplying the pipes in coils of long lengths.

For this project in particular, the well had to be installed in a central area of the city and therefore there was not enough space to carry out the coil deployment. The pipe needed to transport treated effluent water.

Pexgol Solution

Together with the Engineering Department of Golan Plastic Products, low cost accessories were developed in order to be able to install the pipes in 12 meter lengths and thus occupy as little space as possible on public roads for installation.

The accessories consisted of a stainless steel “insert” and our Double Connector made of galvanized iron coated on the outside with anti-corrosive paint. Although long sections were not supplied, the fact of installing Pexgol pipe guarantees a long lifespan, which could not be achieved if it was done with conventional steel pipes.

The installation was a success and only took one working day, to make the connections the team did not require special tools or previous training.

Related Case Studies

Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019