Installation of Water Well in Reduced Space

Installation of a Borehole with Pipe in Sections for Reduced Space.

Estudo de Caso Nº

95

Cliente

Mekorot
Israel

|

2020

Condições de Trabalho

Pressure: 10 bar

Solução Pexgol

Pexgol 200 mm (6”), class 24

Aplicação

Borehole for treated effluent water

Comprimento

70 m

Categorias

Installation of a Borehole with Pipe in Sections for Reduced Space.

The Challenge

Mekorot, the national company in charge of water supply in Israel, among other activities, has installed and used Pexgol pipes for water wells for more than 30 years.

The wells were always installed using one of Pexgol’s great advantages, which is the possibility of supplying the pipes in coils of long lengths.

For this project in particular, the well had to be installed in a central area of the city and therefore there was not enough space to carry out the coil deployment. The pipe needed to transport treated effluent water.

Pexgol Solution

Together with the Engineering Department of Golan Plastic Products, low cost accessories were developed in order to be able to install the pipes in 12 meter lengths and thus occupy as little space as possible on public roads for installation.

The accessories consisted of a stainless steel “insert” and our Double Connector made of galvanized iron coated on the outside with anti-corrosive paint. Although long sections were not supplied, the fact of installing Pexgol pipe guarantees a long lifespan, which could not be achieved if it was done with conventional steel pipes.

The installation was a success and only took one working day, to make the connections the team did not require special tools or previous training.

Estudos de Caso Relacionados

Profertil and the Adaptation to New Chemical Processes with Pexgol.

Efficient Implementation of NaOH Drainage Systems

Pluspetrol
Argentina

 | 

2023
Greater operational efficiency with fewer joints and fast implementation.

Fresh Water Line Optimization in an Oil Field in Argentina

Phoenix Global Resources
Argentina

 | 

2025
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Pan American Energy implements an efficient and sustainable solution for brine transportation.

Fast and Safe Brine Transport in the Salar de Hombre Muerto

Lithos (PAE)
Argentina

 | 

2024