Skip to content

Environmental Protection and Efficiency in Tailings Management

In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Case Study Nº

122

Customer

Mina Capella – Grupo Peñoles
Mexico

|

2023

Working Conditions

Flow: 200 m3/h Temperature: 25°C / 77°F Pressure: 130psi Fluid components: Limestone, water and acids – 55% solids in suspension. Specific weight 3. K50 (microns): 91.3

Pexgol Pipes

Pexgol 225 mm (8″), Class 15

Application

Transport of Slurry

Lenght

900 m / 2952 ft

Categories

Environmental Protection and Efficiency in Tailings Management

The Challenge

At the Mina Capela mining complex of Grupo Peñoles in Mexico, they faced the challenge of implementing an efficient and safe solution for pumping tailings from the thickener plant to a new tailings dam. The solution had to be wear-resistant in the long term and ensure minimal risk of leaks to protect the environment.

Pexgol Solution

The choice was to install 900 meters of Pexgol 225 mm (8”) Class 15 piping, known for its durability and abrasion resistance. The piping was arranged around the tailings dam, with branches every 200 meters to fill the dam from different positions, thus optimizing the distribution of material.

The main challenges to face were:

  • Highly abrasive fluid: The tailings required a solution that could withstand longterm
    wear.
  • Environmental protection: In case of spillage, the fluid could negatively affect
    the local ecosystem.

Therefore, an option with minimal risk of leaks in the piping and connections was sought.

The Pexgol 225 mm (8”) Class 15 piping proved to be the ideal solution for this challenge. The combination of the material’s (PE-X) abrasion resistance and the supply in rolls, which minimizes the number of joints, made Pexgol the safest option.

After three years of operation, thickness measurements taken every six months have confirmed that there has been no reduction in the thickness of the piping, demonstrating its durability and optimal performance.

Related Case Studies

Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Efficient Choice: PE-X Pipe for the Palm Industry

Extractora Monterrey
Colombia

 | 

2023
Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018