Alumina Plant: Ore Slurry Transportation
Transportation of Bauxite Ore Slurry at 95°C / 203°F
Case Study Nº
52
Customer
Urals Alumina Plant – Rusal
Russia
|
2013
Working Conditions
High temperature
Pexgol Pipes
Pexgol 160 mm Class 15
Application
Slurry Transportation
Lenght
20 m
Categories

The Challenge
At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.
Pexgol Solution
The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.
The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.
Related Case Studies
Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport
Syncrude
Canada
|
2022
Drainage in Underground Mine
Atacama Kozan
Chile
|
2019
Transporting Brine at High Pressure
Mekorot
Israel
|
2020
Transport of Compressed Air for Underground Mine
HMC Gold
Chile
|
2021
Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport
Buena Vista del Cobre
Mexico
|
2024