Compressed Air Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Case Study Nº

41

Customer

Saucito S.A. de C.V. Mine
Mexico

|

2017

Working Conditions

Pressure 205-262 psi; Temperature 60°C to 71°C / 140° F to 159.8°F.

Pexgol Pipes

Pexgol SDR 6 110×18.3.

Application

Compressed air transportation.

Lenght

600 meters.

Categories

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client decided to replace their current HDPE pipe lines which transported compressed air at 60°C to 71°C / 140° F to 159.8°F.

The reason for replacing the HDPE pipes was serious leaks on the thermo-fusion joints.

As one possible reason for these failures, the client pointed out that the maximum allowed temperature of the HDPE pipes was just up to 45°C / 113°F.

Pexgol Solution

In order to solve this problem, Saucito Mine decided to replace their HDPE pipes for Pexgol pipes.

Beside their high temperatures resistance up to 110°C / 230°F, Pexgol pipes are not connected by thermo-fusion joints. They are supplied in 600 meters long sections with very few connections.

The installation was fast and efficient and no sophisticated tools were necessary.

Related Case Studies

Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
Pexgol extends pipe lifespan and reduces maintenance in salt production.

Fewer Shutdowns, Greater Efficiency: Pexgol in the Salt Industry

Sales del Istmo
Mexico

 | 

2023
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019