Mine Dewatering at Low Temperature

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Case Study Nº

61

Customer

Ferrexpo Yeristovo Mining
Ukraine

|

2019

Working Conditions

Vertical installation, ground laying on hills. Ambient temperature: -15°C to 4°C

Pexgol Pipes

Pexgol 280 mm (10”), Class 15

Application

Mine Dewatering

Lenght

360 m

Categories

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

The Challenge

Ferrexpo Yeristovo Mining needed to install mobile long sections of pipeline for mine dewatering. They requested that the pipe should have scratch resistance and can be installed on the rocks without any complicate preparations.
They used to work with steel pipes but they presented serious problems such as:

  1. Corrosion
  2. Difficult and expensive installation
  3. Long disassembly and replacement time

Pexgol Solution

The client chose Pexgol pipes with 280 outside diameter, class 15 in coils of 120 meters each with mechanical couplers for a fast and efficient installation. During the installation a 60 ton Hitachi bulldozer and a Manitou telehandler were used for decoiling.

There were 3 separated lines of one piece of 120 meters each without any additional connectors. The only connection was a flange coupler with a pump outlet. Pipes were fixed on top and in the middle by fixpoint clamps as well.

The use of Pexgol pipe solutions allow the client to save costs (manpower and installation time).

Related Case Studies

Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019