Water Drainage at an Underground Mine

Water Drainage From the Inside of an Underground Mine

Case Study Nº

31

Customer

El Peñón Yamana Gold, Meridian Mine
Chile

|

2016

Working Conditions

Extreme temperatures (-5° to 38°C).

Pexgol Pipes

Pexgol 160 mm Class 15 (SDR 11).

Application

Water drainage.

Lenght

600 m.

Categories

Water Drainage From The Inside Of An Underground Mine

The Challenge

The water drainage from the inside of Meridian underground mine was processed through an HDPE 12 meter pipe that required 50 joints to be installed. The total installation time was 4 days, with no chance to minimize costs. Furthermore, the pump operated over it efficiency levels.

Pexgol Solution

A 600 meters Pexgol pipe 160 mm Class 15 was provided, in one section without joints. The Pexgol pipe was carried for 6 kilometers in 2 turns, which caused as a result 50% of time saved in the installation.

Due to the lower load losses, now the pump operates at its mayor efficiency level.

Related Case Studies

Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023