Open Cast Mine Dewatering

Dewatering With Low Ph Levels

Case Study Nº

34

Customer

Arcelor Mittal Mine
Mexico

|

2016

Working Conditions

Pressure 400 Psi; height difference: 220 m; specific weight 1.15 t/m3; solids 15-20%.

Pexgol Pipes

Pexgol 8” (225 mm).

Application

Dewatering

Lenght

Sections of 280 m.

Categories

Dewatering With Low Ph Levels

The Challenge

Arcerlor Mittal required to dewater their open cast mine, due to the contamination produced by the low pH levels of the water.

The open cast was 220 meters depth with an 80° slope. From the client point of view, installing a regular pipe would involve doing more than 22 joints, on a harsh ground that was also dangerous for the people that work there. In addition, a regular pipe might need to be supported every 12 meters so it will not collapse due to its own weight.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Related Case Studies

Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022