Open Cast Mine Dewatering

Dewatering With Low Ph Levels

Case Study Nº

34

Customer

Arcelor Mittal Mine
Mexico

|

2016

Working Conditions

Pressure 400 Psi; height difference: 220 m; specific weight 1.15 t/m3; solids 15-20%.

Pexgol Pipes

Pexgol 8” (225 mm).

Application

Dewatering

Lenght

Sections of 280 m.

Categories

Dewatering With Low Ph Levels

The Challenge

Arcerlor Mittal required to dewater their open cast mine, due to the contamination produced by the low pH levels of the water.

The open cast was 220 meters depth with an 80° slope. From the client point of view, installing a regular pipe would involve doing more than 22 joints, on a harsh ground that was also dangerous for the people that work there. In addition, a regular pipe might need to be supported every 12 meters so it will not collapse due to its own weight.

Pexgol Solution

Pexgol pipes were the optimal solution for this project, because it can be supplied in long lengths coils that makes the whole installation easier.

Pexgol is also known for its stress resistance, Pexgol’s crosslinking piping solution can withstand high amounts of axial and radial stresses, it only stretches up to 2% of its own length and it is capable to hold its own weight plus the water column.

Due to it great flexibility, the coil was uncoiled hundreds of meters away from the installation place, and it was dragged after to the right spot.

In order to descend the pipe through the open cast, it required only chains and a backhoe to hold it. Arcelor Mittal was very satisfied with the installation process, which was simple, and from their point of view, impossible to do it with other type of pipe.

Related Case Studies

Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
 How Pexgol streamlined water transportation at Zuccardi Winery

Fast and Reliable Solution for Winemaking Processes

Zuccardi Winery
Argentina

 | 

2024
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023