Skip to content

Replacement of Steel Pipes for PE-X

Replacing Steel for PE-X Pipes to Transported Processed Water.

Case Study Nº

105

Customer

Rosebel Gold Mines – IamGold
Suriname

|

2020

Working Conditions

Pressure: 60 PSI | Flow: 70 m3/h | Temperature: 45°C | Fluid: Processed water

Pexgol Pipes

Pexgol 225 mm (8”)

Application

Processed water transportation

Lenght

100 m / 328 ft + elbows + tees + reducers

Categories

Replacing Steel for PE-X Pipes to Transported Processed Water.

The Challenge

At the Rosebel Gold mine they had serious scale problems in the water transport line for the SAG Fees Chute mill.

They generally used steel pipes that ended up becoming encrusted, which resulted in them needing to be cleaned and on many occasions changed in periods of 3 to 5 months. This generated losses in production and a large cost for the maintenance that the steel required. Additionally, in the periods of use, the pumping pressures had to increase since the internal diameter of the pipe was reduced.

Pexgol Solution

The client was aware of the advantages of Pexgol to prevent fouling in lime slurry transport applications and therefore it was decided to proceed with a first section for testing.

With the Pexgol piping system, which has a low internal roughness, long radius elbows and mechanical accessories were supplied that helped ensure that even between the joints there were no interferences.

Today the system has been working for more than 10 months without problems or fouling, which is already a success for the client since its installation is simple and the costs are lower than steel pipes.

The connections were mechanical, it was only necessary to cut the pipe to size and place screws. PE-X is much lighter than steel, so fitting it to the pipe racks was also simple.

Additionally, the plant has Victaulic-type connections on the steel pipes, which made the job simple as Pexgol can also connect with Victaulic.

Related Case Studies

Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013