Transport of Compressed Air

Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Case Study Nº

66

Customer

Meridian Mine – Faena El Peñón
Chile

|

2018

Working Conditions

Pressure: 10 bar

Pexgol Pipes

Pexgol 160 mm (6”), Class 15

Application

Transport of compressed air

Lenght

1800 m

Categories

Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

The Challenge

The Meridian Mine (Faena El Peñón) required the installation of a line for the transport of compressed air from the surface (horizontal), crossing roads of mining vehicles, ending 200 meters deep inside an underground mine through a vertical chimney.
The line had to withstand 10 bar of pressure.

Pexgol Solution

The client decided to install a 160 mm (6”) Pexgol pipe class 15 SDR 11 of 1800 meters in coils of 600 meters each.
Pexgol pipe was selected due to it advantages:

  • Less joints were needed, contributing to saving costs and giving more reliability to the line.
  • Resistance to mechanical stresses involved in installing at mining crossroads, using a 1.5 meter ditch and filling with material from the same ditch, without using a steel jacket.
  • Resistance to changes in ambient temperature (5°C to 30°C).
  • Creep resistance.

The installation was simple: only 4 mechanical connections were used, selected by the mining company without using special tools. If HDPE pipes were used, about 150 mechanical connections would have been required.

Also, to support the Pexgol pipes in the upper zone, before entering the underground mine by the chimney, a mechanical system designed by the mining company was incorporated.

Related Case Studies

Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Addressing Scaling and Line Plugging with Advanced PE-X Piping.

Slurry: Pexgol’s Superior Alternative to Traditional Piping

Chip Manufacturer
USA

 | 

2022
Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022