Transport of Muddy Water in a Palm Oil Processing Plant

Transport of Muddy Water (Pome) witha High Content of Organic Load.

Case Study Nº

85

Customer

La Gloria
Colombia

|

2020

Working Conditions

Temperature: 80°C | Flow: 36m³/h

Pexgol Pipes

Pexgol 110 mm (4″), clase 12

Application

Muddy water transportation

Lenght

1200 m

Categories

Transport of Muddy Water (Pome) witha High Content of Organic Load.

The Challenge

La Gloria, a company dedicated to the extraction of palm oil in César (Colombia), required a new line to transport muddy water to the oxidation ponds. From the florentino lagoon (treatment pool), passing through the main road and the plantation, the excavation and installation of the pipe had to be carried out in the crop, between palms without causing damage to the plants and the irrigation pipe. In addition, given the operating conditions and the type of fluid, a pipe was required that resists high temperatures and has a low internal roughness index due to incrustations.

Pexgol Solution

Due to the high costs of carbon steel pipe, added to the cost of assembly, it was decided to use Pexgol pipes.

Pexgol was selected for its quick and easy installation, fewer joints and the possibility of supplying it in rolls.

The installation of the 1200 meters was carried out in 4 hours. Four electrofusion joints were used for the splicing of the sections and a mechanical joint was used at each end.

Related Case Studies

Grey Water Transportation

Recovered Water Transportation

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

 | 

2017
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023