Installation of Water Well in Reduced Space

Installation of a Borehole with Pipe in Sections for Reduced Space.

Case Study Nº

95

Customer

Mekorot
Israel

|

2020

Working Conditions

Pressure: 10 bar

Pexgol Pipes

Pexgol 200 mm (6”), class 24

Application

Borehole for treated effluent water

Lenght

70 m

Categories

Installation of a Borehole with Pipe in Sections for Reduced Space.

The Challenge

Mekorot, the national company in charge of water supply in Israel, among other activities, has installed and used Pexgol pipes for water wells for more than 30 years.

The wells were always installed using one of Pexgol’s great advantages, which is the possibility of supplying the pipes in coils of long lengths.

For this project in particular, the well had to be installed in a central area of the city and therefore there was not enough space to carry out the coil deployment. The pipe needed to transport treated effluent water.

Pexgol Solution

Together with the Engineering Department of Golan Plastic Products, low cost accessories were developed in order to be able to install the pipes in 12 meter lengths and thus occupy as little space as possible on public roads for installation.

The accessories consisted of a stainless steel “insert” and our Double Connector made of galvanized iron coated on the outside with anti-corrosive paint. Although long sections were not supplied, the fact of installing Pexgol pipe guarantees a long lifespan, which could not be achieved if it was done with conventional steel pipes.

The installation was a success and only took one working day, to make the connections the team did not require special tools or previous training.

Related Case Studies

Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992
Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
Field evaluation of Pexgol PE-Xa pipes under highly abrasive iron ore slurry conditions at Cauê Mine.

Test Case – Field Performance Evaluation of Pexgol

Vale
Brazil

 | 

2025
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Installation of Pexgol Pipes for Transporting Hot Water.

Hot Water Supply

Hilton
Israel

 | 

2020