Skip to content

Transportation of sodium sulfide

Pvc Pipe Replacement by Pexgol

Case Study Nº

44

Customer

Magnelec S.A. de C.V.
Mexico

|

2018

Working Conditions

Pressure 60 psi; Temperature 60° to 80°C; Highly Corrosive Liquid

Pexgol Pipes

Pexgol 225×20.4 SDR 15

Application

Sodium Sulfide Transportation

Lenght

600 meters

Categories

Pvc Pipe Replacement by Pexgol

The Challenge

Magnelec had installed a Yellomine pipe (PVC pressure pipe) where it was transporting sodium sulfide.
Due to changes in temperature in the fluid, dilatation and contraction of the pipe was frequent issue. The pipe was installed in sections of 6 metersc each, generating leaks in the joints, which caused a lot of losses in the line of conduction. Also, there were problems in the stainless steel pipes with leaks in the joints of the welds.

Pexgol Solution

Due to this frequent problems, Magnelec decided to replace its pipes with Pexgol. Once the Yellomine pipes were replaced by Pexgol pipes, the problem of leakage was solved, thanks to the fact that Pexgol pipes were supplied in rolls of great lengths, which decreased the number of joints. The material of Pexgol pipes is flexible and absorbs the movements that can be generated by changes in temperature.
They are also highly resistant to corrosion and to high and low temperatures, so it was the ideal solution.
The installation was quick and easy in sections of 200 meters in length with mechanical GP connections. The installation took around 7 days. The tools used were tightening wrenches, slings, crane, etc.

Related Case Studies

The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Water Drainage From the Inside of an Underground Mine

Water Drainage at an Underground Mine

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016