The Challenge

At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.

Pexgol Solution

The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.

The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.

Related Case Studies

Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017