Cold Water Distribution for External Cooler System

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Case Study Nº

115

Customer

Chip Manufacturer
Israel

|

2022

Working Conditions

Pressure: 6 bars | Temperature: 8°C / 46°F

Pexgol Pipes

Pexgol 355 (14″), 400 (16″) & 630 (24″) mm, Class 15

Application

External Chiller System

Lenght

160 m / 525 ft

Categories

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to increase the capacity of energy in the factory by adding an external chiller system and they needed to finish the installation and implementation as soon as possible.

Pexgol Solution

Due to a successful experience in the past, the company decided to use Pexgol pipes due to the fast installation time, helping to maintain their operation schedule and reduce the total cost of the project.

Related Case Studies

Comparative Test for the Transport of Brine with HDPE and Pexgol Pipes.

Comparison of brine transport

Albemarle Salar
Chile

 | 

2020
Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Minas Argentinas Replaces HDPE with Pexgol in Its Secondary Leaching Project

Efficient and Safe Irrigation in Secondary Leaching with Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015