Skip to content

Comprehensive Water Transportation Solution for Urgent Projects

How Pexgol Accelerated the Supply and Installation of a Critical Line.

Case Study Nº

170

Customer

Madagascar Mining
Madagascar

|

2024

Working Conditions

Temperature: 25°C / 77°F | Flow Rate: 300 m³/h | Pressure: 28 bar | Fluid Components: Sand

Pexgol Pipes

Pexgol 280 mm (10″) class 30, 24, 19 & 15

Application

River Water Transportation

Lenght

6 km

Categories

Comprehensive Water Transportation Solution for Urgent Projects

The Challenge

A leading mining operation focused on nickel and cobalt extraction and refining in Madagascar, faced a critical challenge: ensuring a reliable water supply to its pulp plant. This required building a 6-kilometer pipeline from the nearest river to the plant.
Although the project design seemed straightforward, two key challenges emerged:

  1. High Pressure Requirements: With a height difference of 160 meters and friction losses across the 6-kilometer distance, the pipeline needed to withstand pressures of up to 28 bar.
  2. Project Urgency: The plant was running out of water, meaning the project had to be executed quickly — from pipe supply to installation — with limited resources.

The Solution

Pexgol provided an ideal solution for this project by supplying 280 mm (10”) pipes in classes 30, 24, 19, and 15. These pipes were selected due to their ability to handle high pressures, flexibility, and ease of installation. Additionally, they were supplied in long coils of 100, 200, and 300 meters, which significantly reduced the number of required connections.

The fitting system used included electrofusion couplings, flared ends, and loose flanges, ensuring secure and quick connections. Pexgol’s technical support covered the entire process, from design to on-site installation, including training and tools to optimize the project’s execution.

Ambatovy evaluated alternative solutions such as steel flexible pipes with PE coatings but ruled them out due to long delivery times and the need for specialized installation tools. Pexgol proved to be the most efficient and viable solution, providing a fast, tailored response to the client’s needs.

Pexgol’s performance in this project highlights its ability to overcome technical and logistical challenges in demanding conditions.

Related Case Studies

Water Extraction From A Middle Pool To The Exterior Of The Mine

Dewatering at an Open Cast Mine

Codelco, Ministro Hales Division
Chile

 | 

2016
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022