Skip to content

Corrosive Material Transportation

Transport of high corrosive material from the thickeners to the neutralization plant

Estudo de Caso Nº

23

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2015

Condições de Trabalho

70° C, 11 bars.

Solução Pexgol

Pexgol 500 mm, Class 15 and Pexgol 450 mm, Class 15.

Aplicação

Transportation of corrosive material.

Comprimento

150 m.

Categorias

Transport of high corrosive material from the thickeners to the neutralization plant

The Challenge

Moa Nickel required to transport high corrosive material from the thickeners to the neutralization plant tanks. Originally, they used to do it through a 18 and 16 inches carbon steel line (A53, Gr.B, Sch10), with welded joints and 1/4” rubber lined. The pipe consisted in short pipe sections, 6 meters long each one, approximately 150 meters total length. It was used until it was practically destroyed as a consequence of the corrosion and wear. The engineering team decided that it needed to be replaced before it could affect the production.

Pexgol Solution

Golan presented a quick-to-install solution for the complete substitution of the line. The design included standard and special Pexgol fittings, elbows, Tee instruments and more than 150 meters of pipe. The Pexgol pipe was installed in the same spot as the former carbon steel pipe, improving the supports.

The former carbon steel pipe was 50% more expensive than Pexgol, which also was more convenient and easy to install, saving time and money for its installation.

 

Pipe TypePexgol Cost vs OthersPexgol Total Investment Costs vs Others
Rubbed steel A53 Gr, B Sch. 201:1.41:2
Stainless steel 316L, Sch. 201:21:3
Titanium B862, Gr.2, 3 mm thk1:2.31:3.2
Polypropylene PP-H, SDR 171:3.81:4.2

Estudos de Caso Relacionados

Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021