Skip to content

High Pressure Water Transport

High Pressure Water Transport for a Gold Mine.

Case Study Nº

86

Customer

Mansfield Mine
Argentina

|

2019

Working Conditions

Exposed pipe with repump systems at 21 bar (305 PSI)

Pexgol Pipes

Pexgol 225 mm (8″), class 24, 19, 15 & 12

Application

Water transport

Lenght

12.5 km

Categories

High Pressure Water Transport for a Gold Mine.

The Challenge

The engineering company SAXUM had the challenge of designing the main water supply line for Mansfield’s “Lindero Gold Mine” project, which through heap leaching removes and processes mineral.

Given the differences in height (more than 300 meters in total) and the length, a pipe was required that would provide safety to work with high pressures and that can be exposed to the sun without the need to bury it.

Due to the climatic conditions of the area, with low temperatures and strong winds, added to the height (above 4000 m above sea level), a simple and quick solution to install was sought, since otherwise the costs of assembly would be very high.

Pexgol Solution

It was decided to install Pexgol since it is supplied in coils, in this case up to 280 meters in length. Compared to steel and HDPE supplied in 12 or 14 meter lengths, this supply format kept labor and the posibility of failure to a minimum.

Approximately 1,400 meters were installed per day with only three operators and a backhoe. The connections were made by electrofusion couplings.

Related Case Studies

Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020