Improvement in Brine Management through Pexgol Piping

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Case Study Nº

128

Customer

Sales de Jujuy
Argentina

|

2023

Working Conditions

Temperature: Variable

Pexgol Pipes

Pexgol 160 mm (6″), Class 15

Application

Brine Transport

Lenght

2650 m / 8692 ft

Categories

Improvement in Brine Management through Pexgol Piping

The Challenge

Sales de Jujuy S.A. is the operating company of the main Olaroz Lithium Project by Orocobre in Argentina. This facility is located in the province of Jujuy, at an altitude of 3,900 meters above sea level, and produces lithium carbonate from the brine of the Olaroz Salt Flat, which contains high concentrations of lithium and potash. The transportation of brine from the lithium well posed a significant challenge for the company.

The problem lay in the existing HDPE pipeline, which experienced a pump performance drop three times a month when pumping brine. This situation was caused by pipe clogging due to scale buildup, requiring cleaning that consumed six working days per month. This not only disrupted regular operations but also incurred significant costs for the company.

Pexgol Solution

To address this challenge, Sales de Jujuy decided to switch to 160 mm Pexgol piping. They installed 2650 meters of this piping, using double mechanical connectors.

The choice of Pexgol was due to several advantages that this product offered. Firstly, its quick installation significantly reduced the time required for project implementation. Additionally, Pexgol piping is known for its low roughness, which considerably reduces scale buildup.

This change to Pexgol brought immediate and significant results. Line cleaning times and the number of interventions were drastically reduced. In fact, the cleaning time was reduced to only two hours per month, and only at the connections.

Related Case Studies

Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Replacement of a Drainage Line in an Underground Mine.

Drainage in Underground Mine

Atacama Kozan
Chile

 | 

2019
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
Improving drainage in the Media Luna mine with Pexgol.

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Minera Media Luna
Mexico

 | 

2023