Improvement in Brine Management through Pexgol Piping

The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Case Study Nº

128

Customer

Sales de Jujuy
Argentina

|

2023

Working Conditions

Temperature: Variable

Pexgol Pipes

Pexgol 160 mm (6″), Class 15

Application

Brine Transport

Lenght

2650 m / 8692 ft

Categories

Improvement in Brine Management through Pexgol Piping

The Challenge

Sales de Jujuy S.A. is the operating company of the main Olaroz Lithium Project by Orocobre in Argentina. This facility is located in the province of Jujuy, at an altitude of 3,900 meters above sea level, and produces lithium carbonate from the brine of the Olaroz Salt Flat, which contains high concentrations of lithium and potash. The transportation of brine from the lithium well posed a significant challenge for the company.

The problem lay in the existing HDPE pipeline, which experienced a pump performance drop three times a month when pumping brine. This situation was caused by pipe clogging due to scale buildup, requiring cleaning that consumed six working days per month. This not only disrupted regular operations but also incurred significant costs for the company.

Pexgol Solution

To address this challenge, Sales de Jujuy decided to switch to 160 mm Pexgol piping. They installed 2650 meters of this piping, using double mechanical connectors.

The choice of Pexgol was due to several advantages that this product offered. Firstly, its quick installation significantly reduced the time required for project implementation. Additionally, Pexgol piping is known for its low roughness, which considerably reduces scale buildup.

This change to Pexgol brought immediate and significant results. Line cleaning times and the number of interventions were drastically reduced. In fact, the cleaning time was reduced to only two hours per month, and only at the connections.

Related Case Studies

Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015
Hot sylvinite leach at 114°C/237°F

Mineral Processing – Potash Processing Plant

ICL group, Dead Sea Works
Israel

 | 

1987
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022