Alumina Plant: Ore Slurry Transportation
Transportation of Bauxite Ore Slurry at 95°C / 203°F
Case Study Nº
52
Customer
Urals Alumina Plant – Rusal
Russia
|
2013
Working Conditions
High temperature
Pexgol Pipes
Pexgol 160 mm Class 15
Application
Slurry Transportation
Lenght
20 m
Categories
The Challenge
At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.
Pexgol Solution
The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.
The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.
Related Case Studies
Meltdown Water Transport
Codelco Andina, TADA 1-2 Project
Chile
|
2013
Mining Drainage Lines
Lundin Mining – Alcaparosa Mine
Chile
|
2019
Vertical Dewatering
Ferrexpo Poltava Mining
Ukraine
|
2019
Open Cast Mine Dewatering
Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile
|
2013